Yılsan Yatırım Holding
Karayel Elektrik

Wind

Karayel Elektrik

Karayel Elektrik

Kırklareli, Vize · Temmuz 2020

Vize-2 WPP stands out with its modern engineering design developed in harmony with the environment, its technological infrastructure that utilizes renewable energy sources with optimum efficiency, and its vision for sustainable energy generation; at the same time, it makes significant contributions to the clean energy transition, the reduction of carbon emissions, and energy supply security.

52% of the total electromechanical equipment used in the project has been manufactured in Türkiye; domestic production solutions have been preferred for generators, towers, blades, and auxiliary equipment. In this way, engineering optimization, shorter procurement timelines, easier access to spare parts, and high continuity in operation and maintenance processes were achieved. This approach strongly demonstrates that the project has been implemented in line with the understanding of domestic and national production.

The first turbine of Vize-2 WPP was commissioned in July 2020, and with subsequent additional investments, its capacity was regularly increased to reach full capacity.

It has an average annual electricity generation capacity of 460 million kWh. This level of production is sufficient to meet the yearly electricity needs of thousands of households.

Within the scope of the project: 16 units of Nordex N149 model turbines, each with a capacity of 4.8 MW and a hub height of 125 meters; 4 units of Nordex N163 model turbines, each with a capacity of 7 MW and a hub height of 118 meters, have been utilized.

Capacity expansion is ongoing with 3 additional turbines, each with a capacity of 7 MW. These turbines have been selected based on their high efficiency and low environmental impact.

Technical Specifications

Licensed Installed Capacity125.8 MW
Average Annual Expected Generation460 Million kWh
Ratio of Equipment Manufactured in Türkiye52%
Annual Carbon Reduction193,960 Tons
Turbines16 × Nordex N149 (4.8 MW, 125 m hub height) + 4 × Nordex N163 (7 MW, 118 m hub height)
Capacity Expansion3 × 7 MW turbines (ongoing)
Coordinates35 T 561969.92 E, 4611342.60 N

125.8 MW

Installed power

460 million kWh

Annual output

1 / 8