Hydroelectric

DNZ

DNZ

Denizli, Çal · 22.11.2013

The construction of the Akkent-Çalkuyucak HPP along the Büyük Menderes River in Denizli’s Çal district was completed, and the plant was put into operation on 22.11.2013.The construction of the Akkent-Çalkuyucak HPP along the Büyük Menderes River in Denizli’s Çal district was completed, and the plant was put into operation on 22.11.2013.

The project was designed to have a weir, 4-km tunnel, forebay pool and a penstock (89 m head 1.5 m diameter). The plant is capable of handling 18 m³ water per second.

Project construction was undertaken by Kuzey İnşaat Makina A.Ş while electromechanical equipment was supplied by the ANDRITZ Hydro (France) & INDAR consortium.

Proposed annual energy production capacity of the plant is almost 40 million kWh.

Technical Specifications

Project Flow18.10 m3/sn
Number of Units3 Francis Turbines
Installed Power13.813 MWe
Power Generated39,840,000 KWh